Scope of works performed:
- 36 Month Project
- Principle Contractor.
- Design documentation including grading studies
- 6 x new 4000A Consumer Mains
- 9 x New 4000A Main Switchboards,
- 6 x New Power Factor Correction Units
- 5 x New Generator Switchboards,
- 29 x New ATS replacements and in new Switchboards,
- 16 x New Manual Transfer Switches
- 32 x New Specialised Services MDBS and Switchboards
- 8 x Tenant Load Shedding switchboards
- 6 x New Specialised MCC Switchboards
- New House UPS system
- New House Switchboards
- New Tee off boxes
- New House and Tenant Risers,
- New Energy Monitoring System and meters
- New PLC and Scada Control Systems including 6 x PLC panel switchboards
- 6 x 1000kVA Generator Synchronisation over three different floors
- Generator Starter and DC Battery System Replacement
- Generator Fuel System Replacement
- Moving and Re terminating 36 x MIMS cabling
- Dual Redundant Fibre Backbone and control cabling for PLC – SCADA systems
- General Light and Power