Scope of works performed:
- 21 Month Project.
- Principle Contractor.
- Design documentation including grading studies
- 4 x New 4000A Main Switchboards,
- 4 x New Generator Switchboards,
- 31 x New ATS replacements and in new Switchboards,
- 2 x New Manual Transfer Switches
- 88 x Fused Tee off box
- 8 x Tenant Load Shedding switchboards
- 3 x New Generator MCC Switchboards
- New House and Tenant Switchboards
- New House and Tenant Risers,
- New PLC and Scada Control Systems
- 3 x 1875kVA Generator Synchronisation
- Generator upgrade works
- Generator Starter and DC Battery System Replacement
- Generator Fuel System Replacement
- 3 x 400kW load banks
- New Fire Rated and Non-Fire Rated Submains
- Moving and Re terminating MIMS cabling
- Removing redundant MIMS cabling
- Dual Redundant Fibre Backbone and control cabling for PLC – SCADA systems
- Mains, Submains, Cable pathways,
- General Light and Power
- General Builders Works.