Resmed Australia Stages 2 And 3

The Resmed Stage 2 project involved the construction of the main flagship campus building consisting of some: 23,000m2 of office space over eight levels with commercial kitchen, a canteen, five lifts, pool area, gymnasium, 530 workstations, 30 offices, 16 meeting rooms, several laboratories, data centre and acoustic testing chambers, group training rooms and 3 levels of in-ground car parking and plant rooms. Once completed, Resmed continued their campus expansion with the Stage 3 LSR Manufacturing project that included the expansion of the existing hygienic manufacturing facilities with production moulding facilities and storage warehousing.

Barnwell Cambridge were engaged for the installation and integration of the electrical services for Resmed Stage 2, where we were then invited to compete the stage 3 project based on the previous project success. The vast building included emerging technologies that included Dali lighting and bespoke communications networks with multiple communications Hub rooms per floor, and campus data centre.

The services provided included,
⦁ High Voltage Substation
⦁ Standby Generator
⦁ UPS System
⦁ Main Switchboards and Main Distribution Boards
⦁ General Distribution Boards
⦁ Power Factor Correction
⦁ Mains and Submains Cabling
⦁ LV and Communications Cable Pathways.
⦁ In Ground Conduit and Pathways
⦁ Specialist Cabling for production plant.
⦁ General Lighting and Power
⦁ Soft Wired System to Workstations
⦁ Emergency Escape Lighting and Exit Signage
⦁ C-Bus Lighting Control System
⦁ Data Communications Infrastructure Cabling and Horizontal Cabling
⦁ Intrusion Detection System and Access Control System
⦁ CCTV System
⦁ PA System
⦁ MATV
⦁ Fire services.
⦁ Lightning Protection
⦁ Infrared Thermal Scanning
⦁ Testing and Commissioning

The project was recognised as a State Finalist at the NECA industry awards.